2022 1104 Pecatonica Prairie Trail Bridge Replacement

FOR IMMEDIATE RELEASE

November 4, 2022

Contact: Sean Von Bergen

Winnebago County Highway Dept.

Office: (815)319-4034

Fax: (815)319-4001

Jill Heyser

ComEd

Overhead Transmission Engineer

630-576-6757

PECATONICA PRAIRIE TRAIL BRIDGE REPLACEMENT

ComEd has hired Brieser Construction to replace the bridge east of Pecatonica Community Garden Park on the Pecatonica Prairie Trail. The work is scheduled to begin on Monday, November 7, 2022. The scheduled work will require the Pecatonica Prairie Trail to be closed east of the Village of Pecatonica from Jackson Street to Lundgren Road. The work is to be completed by Friday, December 30, 2022; however, the duration of the work and the trail closure is dependent on the weather.